SEWER SYSTEM IMPROVEMENTS
The initial specifications outlined an electrical actuation of a powered trolley movement, but this design was not congruent to the crane's purpose. Our designers suggested a powered bridge with the electricals routed to the center driven bridge, with the crane re-designed to fit into a smaller space than shown on the structural drawings. The customer had actually originally wanted the system to operate in this manner, rather than with a powered trolley, but the original intent had been lost in the specifications and addendums. By working through the design with the customer, we were able to provide them with a crane system that met their functional needs, with a corrosion resistant hoist and weather-proofing included. This was our 6th project for this contractor, and they were pleased with all aspects of our work, including our ability to meet their requirements while making everything fit.
For additional information about this custom crane design, fabrication, and installation project, see the table below,or contact us directly.
SEWER SYSTEM IMPROVEMENTS PROJECT HIGHLIGHTS:
Project Name & Description
Primary: System Design Engineering Analysis Fabrication/Manufacturing |
Secondary: Installation |
Dimensions
Capacity: One (1) ton each Lift Height: 27′ |
Span: Three feet (3′) & Five feet (5′) |
Tightest Tolerances
± 1/16″ |
Material Used
|
Material Finish
Industry for Use
Water Treatment |
In Process Testing/Inspection Performed
Functional Testing |
Volume
2 Cranes |
Delivery/Turnaround Time
Five (5) weeks perfect timing for customer |
Location
Centerville, TN |
Standards Met
Customer Specification |